Drawm Grant charts andand calculate each average turn around time.
開始: 2018年 12月 18日(二) 11:25
到期: 2018年 12月 28日(五) 11:25
process |
P1 |
P2 |
P3 |
P4 |
P5 |
Service time |
120 |
60 |
180 |
50 |
300 |
Use the table of processes and service time, draw Grant charts show the completion times for each process using FCFS, SJN and Round-robin CPU scheduling with the time slice of 60, and calculate each average turn around time.