Drawm Grant charts andand calculate each average turn around time.

開始: 2018年 12月 18日(火曜日) 11:25
期限: 2018年 12月 28日(金曜日) 11:25

process

P1

P2

P3

P4

P5

Service time

120

60

180

50

300

Use the table of processes and service time, draw Grant charts show the completion times for each process using FCFS, SJN and Round-robin CPU scheduling with the time slice of 60, and calculate each average turn around time.